    In short.

    Size PUF thickness for the lowest temperature the room will run at: 60 mm for partitions and AC rooms, 80–100 mm for chillers (+2 to +8°C), 100–125 mm for cold storage at 0°C, 125–150 mm for freezer rooms (–18 to –25°C) and 150 mm+ for blast freezers. Hot, high-radiation sites warrant the higher end of each band; hill and north-east sites can use the lower end.

    On this page4 sections
    1. 01Thickness vs temperature band
    2. 02Ambient & site adjustments
    3. 03Project checklist
    4. 04Frequently asked

    PUF panel thickness is a small spec line in a BOQ but a big lever on long-term refrigeration running cost. Under-spec it and you pay forever in electricity. Over-spec it and you waste capex.

    Thickness vs temperature band

    Indicative thickness ranges used in Indian projects.

    • Partitions / AC rooms: 60 mm
    • Chillers (+2 to +8°C): 80–100 mm
    • Cold storage (0°C): 100–125 mm
    • Ripening chambers: 100 mm
    • Freezer rooms (–18 to –25°C): 125–150 mm
    • Blast freezers: 150 mm+

    Ambient & site adjustments

    Hot, high-radiation sites (Rajasthan, Gujarat, Vidarbha summers) warrant the higher end of each band. Hill / north-east sites can use the lower end.

    Before you commit

    Project checklist.

    • 01Lowest target temperature locked
    • 02Peak ambient for the site confirmed
    • 03Door/dock orientation reviewed
    • 04Roof exposure & radiation factor considered
    • 05Thickness selected with operating life in mind
    Questions

    Frequently asked.

    Short answers from the engineering team. Ask us anything the article does not cover.

    Why does thicker PUF reduce running cost?

    Thicker insulation reduces transmission heat load, so the refrigeration system runs fewer hours per day to maintain temperature — directly lowering electricity bills over the project life.

    PUF panels

    Everything we’ve published on this

    PUF panels overview
    Share your brief

    Planning a PUF panel project?

    Share your brief — our engineering team will respond within 24 hours with an indicative estimate and next steps.

    • An engineer calls backUsually the same working day — someone who can talk loads, layouts and schemes.
    • An indicative estimateCapex range, scheme fit and next steps, before any paid DPR work.
    • No obligationYour details are used only to reply to this enquiry.
    Your details
    Your project

    No spam. Indicative estimate only — final quotation depends on site condition, specifications and current material rates.